Las Virgenes - Calleguas Interconnection Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

The Las Virgenes portion of the project has been completed.

For information on the current status of the Calleguas portion of the project, please visit http://www.cmwd-lvmwdinterconnection.com/

Description

Las Virgenes Municipal Water District and Calleguas Municipal Water District own and operate potable water systems largely dependent on imported water supply. Both agencies are subject to scheduled and unscheduled interruptions of water deliveries that can negatively impact their ability to deliver potable water to their respective customers. On March 10, 2015, LVMWD and CMWD entered into an interconnection agreement in order to improve future reliability of both systems. This interconnection is a cost-effective way to deliver water between agencies if one were to experience a complete or partial supply interruption that did not significantly affect the other agency and would be of mutual benefit to both systems. Additionally, the interconnection would facilitate LVMWD’s filling of the Las Virgenes Reservoir during the winter months. The project would also enable LVMWD to expand recycled water service within its service area through construction of new pipeline laterals and service connections.

LVMWD is responsible for the construction of the South pipeline segment connecting LVMWD’s system (at the Thousand Oaks Boulevard and Lindero Canyon Road intersection) and the proposed Pump Station/Pressure Reducing Station (PS/PRS) site. The proposed South interconnection pipeline will be installed under the southbound lanes of Lindero Canyon Road within the City of Westlake Village, southward from the PS/PRS site to Thousand Oaks Boulevard. The South interconnection pipeline is composed of 4,977 linear feet of 30-inch welded steel pipe.

Project Map

This map shows the location of the interconnection project, north of Thousand Oaks Boulevard and south of Kanan Road on Lindero Canyon Road.

intertie location map

Schedule Updates

This section will list recently completed and upcoming construction activities and will be updated  weekly once construction begins. 

 Recently Completed:  

  • All the fiber conduit has been installed.
  • All 5,000 LF of the 30 inch water main have been installed. 
  • All 1,882 LF of the recycled waterline has been installed. 

Upcoming Field Work:

Week of 7/6/21: Installation of air-vacuums, blow offs, and other appurtenances along the pipeline alignment. Filing of the pipelines for disinfection and testing. Cathodic protection testing

Week of 7/12/21: Connection of new waterline to the main system. This includes overnight work at the intersection of Lindero Canyon Rd and Thousand Oaks Blvd.

Week of 7/19/21: Grind and paving of Lindero Canyon Rd from Thousand Oaks Blvd north one-mile

Public Outreach

At LVMWD, we are committed to maintaining a high level of communication and transparency with our local community. We will regularly update this dedicated webpage to keep you informed of the project. We will also be utilizing mailers, door hangers, social media, and our Everbridge alert system to keep residents informed of construction impacts. We have been working closely with the cities of Westlake Village and Thousand Oaks to finalize traffic control plans, construction sequencing, and specified work hours, all to minimize the impacts to local residents.

Letter to Residents and Businesses Regarding Interconnection Project

 

Environmental Documentation

The Interconnection Agreement between LVMWD and CMWD specifies that CMWD will be the lead agency under CEQA. The final Environmental Impact Report (FEIR) for this project was completed by CMWD. As responsible agency, LVMWD has filed notices of determination for the project in both counties. A copy of the Final Environmental Impact Report can be found here:

http://www.calleguas.com/cmwd-lvmwd-feir.pdf

 

Construction

LVMWD issued a call for bids on July 9, 2020. The Call for bids included optional work for the City of Westlake Village (City). The City work includes installation of new fiber optics conduit and full street repaving along Lindero Canyon Road.

As part of this project, LVMWD will also retain the services of a professional consultant to perform inspection and construction management services during construction, as well as a firm to provide cultural resources training and monitoring in compliance with mitigation measures identified in the Environmental Impact Report.

 

Construction Schedule:

The construction schedule for this project is presented below. This schedule outlines general milestones for the project, and is subject to change as dates approach. As LVMWD nears groundbreaking activities, schedule updates will be provided on this page.

 

Construction Contract Awarded                                                         September 2020

Potholing                                                                                             November 2020

Begin Construction of 30” Pipeline                                                     January/February 2021

Begin Construction of Recycled Water Lines                                     February/March 2021

Repaving of Lindero Canyon Road                                                    April/May 2021

Tentative Completion of Major Construction Activities                      May 2021

 

Contact

For questions related to this project, the LVMWD project manager is:

Oliver Slosser, PE

Senior Engineer

oslosser@lvmwd.com

(818) 585 -7123

 

Project Completion Tracker

status bar

 

Project Photos

Pending

 

Important Notes

 

  • This project is funded by an Proposition 84 IRWM Grant and LVMWD wishes to thank the Los Angeles County Public Works and Department of Water Resources for their support
  • This website is intended to convey information about the south pipeline connection to the PR/PRS station.  Information specific to the construction of the PR/PRS station itself and CMWD’s northern pipeline construction may not be reflected on this site and questions should be directed to Calleguas Municipal Water District.

 

 

Sign up for eNotification to receive information and updates on this project by filling out the short form below.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer